Started 2009 and still current

 

Service: Mechanical Services

 

Value: $15,245,000.00

 

 

A fantastic project to be part of in Christchurch, we have been privileged to undertake for CIAL.

 

 

At peak times during 2010 we had up to 50 skilled staff on site installing the ducting, reticulated heating and chilled water pipe work, 35 Air Handling units, 4 new heat exchangers, 3 new Carrier Chillers, over 100 supply and smoke extract fans, Artesian Well 400 diameter pipe work, 65 Fan Coil Units and many Variable Air Volume units to maintain an accurate temperature throughout the Airport site.

 

 

The Project requires a lot of co-ordination with the Airport management team as throughout the mechanical services installation the airport has been an operating business.

 

 

We have a full time on site office with two project managers and a QS overseeing the project. We have recently been engaged to undertake further work at the airport including the new Koru Club Lounges on level 2 and AIRNZ Hub on the ground floor, this will see us through to the end of 2012.

 

 

We will continue to meet the tight deadlines and look forward to handing over more area successfully.